Friday, March 26, 2010

How Long For Senna To Take Effect

solar energy


It is done! After Monday, the first two mechanics were there and began to mount support rails, as of Wednesday there were significantly more workers! Suddenly, up to 8 men scurried around on our roof and brought rails, module frames, and finally to the solar modules themselves. Amazing how fast it was then! Clock by 13 noon today they were ready! 186 modules were in place! Once again the weather had played wonderfully and the work is not interrupted for one minute. We are left now but a big mountain board for disposal. But this is not a problem, is burned at the earliest opportunity and we are going on the packaging.

Now must come the electricians and wire the whole shebang. In the barn already 4 converters are installed. And a few hundred meters of cable on cable drums are available. We assume that there is going to go on Monday. How will this work needs to be long, we do not know. But we are hopeful we can soon go on line and the money will start earning!

Friday, March 5, 2010

Drill Hole In Fireplace

Moving ahead ...

After more or less chaotic yesterday, one can say that today there is progress! The night was dry and cold crazy, this morning the thermometer To minus 10 degrees. Towards evening snow it should. We pray that, as so often absent here, we have already the first wet spot only by the thawed frost yesterday morning!

At 8 clock this morning the three men are high. And at 12 she already had the clock side dish to the garden and finished a good third of the barn to the street. It is such an unusual sight, the well-illuminated white roof, not to take! But only if the modules are mounted out of it, hardly anything will be on display. Tomorrow night should be all ready, if nothing unexpected happens, such as snow!

Addendum: Of course, to have to start snowing. And not so close.

Thursday, March 4, 2010

Serienummer Pctv System

exciting day!


That was a day with every comfort! Since Saturday we are going to meet our new roof, so that from March 15 to Solarmudule can be installed. So far everything has worked out better than expected. The old asbestos roof was down within 3 days, little damage was repaired and we were really good Dinge.Gestern we have cleaned up nicely for the new roof panels, which should be delivered today, easily unloaded and then make it onto the roof could be.

Well, and then came this morning, the 16-meter-long truck with our new roof. We thought ... But Nope! What had been loaded, the sheets for the gable, which is to be made in April! Nix with roof sheets! Whether we were probably shocked? The driver could not help it, of course, had this morning in Bremen have called his tour and is with what its logistics center had charged him, grumbling going on. We stood there and did not know if we freak out immediately or wait for another 5 minutes should be! Everything was organized, volunteers were ready, and now we had nothing to unload!

shouted angrily the truck driver in his company to, and it turned out relatively quickly that had been mixed up in the logistics center, the delivery numbers. Since our roof is open so now virtually the tar paper that is still on it is about 90 years old and therefore full of holes, and one of our major players have to work again on Monday and thus no longer available, we were really angepisst.Zumal tomorrow it will give the snow. Not the best conditions for an open roof!

called after an hour the company from Bremen then totally coy with us. They found our disks, they would now loaded onto a rented truck parts and immediately send it on its way! So we set ourselves infinitely easier to maintain appropriate plates but still over 14 clock at some point can make and receive. In fact, the truck rolled one around here just before 2:30 clock. And then came the drama part two! The executor, that the boards should be managed properly unloaded, not the weight! Wunderbar! Until we had finally turned a neighbor, who managed to trick then 17 and a forklift to lift our wretched sheets of the truck had passed well over an hour! And the volunteers were so ready all the time, the plates quickly to create the roof. And it's very cold here! It was frozen completely. Finally, finally it was done, both stacks, once at 6.50-meter-long sheets and once with 11 meter long sheets were unloaded! There was a quick cup of coffee to warm up and then in a quick-fix action, the sheets were made up on the roof, using a wooden chute. Fortunately, it went really well and quickly! Pushed below the top 5 men and 3 more were on the roof of the plates and piled them there distributed among each other. Now we hope desperately that the announced tomorrow no precipitation occurs, so that we get the roof re-sealed!